ISM’s October manufacturing report records a Production Index of 59.0 and a Supplier Deliveries Index of 59.1. In the delivery index, a reading above 50 signals slower deliveries. More output and slower supply can coexist.
That is a reason to connect purchasing and production decisions more closely. A production target has limited value if the components needed to meet it arrive in the wrong sequence.
I would review the few materials that can stop the line, not give every purchase order equal attention. For each critical item, compare the required date with the supplier’s confirmed date and the evidence behind that confirmation.
Then agree on an escalation threshold. Procurement should know when to involve production, quality, and the customer team before a shortage reaches the workcell.
The practical goal is fewer surprises at the point of execution. Which material currently has the greatest power to disrupt your schedule?