Permits, starts, and completions answer different questions

VanKpa editorial illustration. A woman reviews grouped cards and a page layout on a board.

The latest available Census construction release as of November 16 separates building permits, housing starts, and completions. October data is scheduled for November 18.

I like that separation because it makes the stages visible. Permission to begin, work underway, and an asset ready for use should not be treated as interchangeable.

In a transformation program, the equivalent might be an approved initiative, a deployed system, and a process people can use reliably. Each stage needs its own evidence.

I would define exit criteria before work begins. Who confirms readiness? What has been tested? What must the next team receive before it accepts the handover?

Progress reporting becomes much more valuable when everyone knows what a milestone actually means. A clean definition can prevent a surprisingly expensive misunderstanding.